Work Methodology for Renovation Works of High-rise Commercial Building
Client: DHAKA CHAMBER OF COMMERCE AND INDUSTRY
65-66, Motijheel Commercial Area, G.P.O. Box No 2641, Dhaka-1000, Bangladesh.
PACKAGE-2:PART-C, D, E: Dismantling & Demolishing, Civil and
Plumbing Work AT DHAKA CHAMBER OF
COMMERCE AND INDUSTRY, 65-66, MOTIJHEEL COMMERCIAL AREA, G.P.O. BOX NO 2641,
DHAKA-1000, BANGLADESH.
Project: Renovation and Restoration with
facelift works at the Dhaka Chamber of Commerce and Industries
Work Methodology of the construction
company WAZIPOINT SYSTEM, for Dismantling
and Rubbish Removing of Brick works, RCC works and Renovation of Aluminium
Work, Air conditioner Relocation, Fire Door Installation, Sanitary & Water
Pipe Lines construction and weather coat & painting works in 6 to 12th
floor building project. The works methodology is divided a per the part of the
works in tender BOQ, Part-c, Part-D & Part-E as below:
PART_C
Below
is a comprehensive work methodology for WAZIPOINT
SYSTEM to execute the dismantling and rubbish removal of brick works and
RCC (Reinforced Cement Concrete) elements, alongside the renovation of
aluminium work, air conditioner relocation, fire door installation, and weather
coat & painting works on a 6th to 12th floor building project. This
detailed approach is designed to ensure safety, quality, and efficiency
throughout the project lifecycle.
1. Project Scope and Pre-Planning
Scope
Definition:
- Dismantling & Rubbish
Removal:
- Brick Works: Systematic deconstruction of brick cladding,
partitions, or facades, ensuring minimal impact on surrounding structures
and effective segregation of debris for recycling or disposal.
- RCC Works: Controlled dismantling through precise saw cuts and
segment removal, with immediate onsite support (shoring/bracing) to
safeguard adjoining structures.
- Renovation & Replacement
Works:
- Aluminium Work: Inspection, cleaning, repair or complete replacement
of aluminium elements such as window frames or cladding for enhanced
performance and aesthetics.
- Air Conditioner Relocation: Safe decommissioning, removal, and reinstallation of
AC units—ensuring electrical isolation and secure mechanical mounting
during transfer from existing installations to new designated positions.
- Fire Door Installation: Removal of outdated door sets (if applicable) and
installation of certified fire doors within designated zones to comply
with updated fire-safety regulations.
- Weather Coat & Painting
Works: Surface preparation, priming,
and application of protective weather coats and final paint finishes on
building exteriors, designed for durability under high-rise environmental
conditions.
Prior
to commencement, a detailed site survey, risk analysis, design review, and
permit confirmation are essential so that all operations respect local
regulations and client specifications 2.
2. Site Mobilization and Temporary Setup
Logistics
and Setup:
- Mobilization: Arrange specialized high-rise equipment (scaffolding,
hoists, tilt tables, dust suppression units) and dedicate storage areas
for tools, materials, and removed debris.
- Site Preparation: Erect safety barricades, establish clearly marked work
zones, and set up designated rubbish collection and segregation areas to
prevent cross-contamination of onsite waste.
- Team Briefing: Conduct comprehensive kickoff meetings to clarify
roles, review risk assessments, outline emergency protocols, and set
communication channels (e.g., radios) among teams.
This
initial phase sets the groundwork for safe and efficient operations on the 6th
to 12th floors.
3. Safety Management and Risk Mitigation
Risk
Assessments & Protocols:
- Perform detailed hazard
analyses for work at height, potential structural instability, and risks associated
with dust and debris.
- Ensure all team members are
equipped with rated personal protective equipment (PPE) such as helmets,
harnesses, eye protection, and safety boots.
- Implement daily toolbox talks,
continuous on-site safety inspections, and maintain open lines of
communication for real-time problem resolution.
Emergency
preparedness includes well-rehearsed rescue plans, availability of first aid
resources, and clearly defined evacuation routes.
4. Detailed Execution Methodology
A. Dismantling & Rubbish Removal of Brick Works
Preparation
& Setup:
- Site Marking: Identify and clearly mark brick sections scheduled for
dismantling; protect adjacent construction elements using temporary
supports where necessary.
- Debris Control: Establish engineered debris collection systems (safety
nets, hoists, and chutes) to capture falling bricks and dust suppression
measures (e.g., water misting).
Execution:
- Manual/Mechanical Removal: Gradually dismantle brick elements using pneumatic
chisels, hand tools, or small demolition machines, ensuring each section
is safely lowered.
- Debris Segregation: Immediately sort and load removed brick materials into
designated containers for recycling or proper disposal while keeping
pathways clear for movement.
B. RCC Works Dismantling & Debris Management
Preparation:
- Structural Assessment: Identify and document areas of RCC that require
removal. Reinforce the surrounding structure using shoring or bracing
techniques to maintain stability throughout the removal process.
- Cutting Lines and Segmentation: Precisely mark cut lines, taking into account
reinforcement layouts and load-bearing considerations.
Execution:
- Controlled Cutting: Use specialized concrete saws (e.g., diamond-blade
saws) to segment the RCC safely.
- Segment Removal: Extract each cut segment sequentially, followed by
immediate installation of temporary supports where necessary.
- Debris Handling: Collect, sort, and compact broken concrete elements,
and ensure effective dust suppression during the cutting process.
C. Renovation of Aluminium Work
Inspection
& Preparation:
- Assessment: Identify worn, corroded, or misaligned aluminium
components requiring repair or replacement.
- Surface Preparation: Clean surfaces using appropriate agents, sandblast or
use corrosion inhibitors, and remove any existing sealant residues.
Execution:
- Component Handling: Carefully dismantle defective aluminium components and
document the existing conditions for quality tracking.
- Reinstallation: Install new or refurbished aluminium elements with
precise alignment and sealing to ensure efficiency, weather resistance,
and aesthetic appeal.
D. Air Conditioner Relocation
Preparation:
- System Shutdown: Isolate and decommission the AC units by safely
disconnecting electrical, plumbing, and refrigerant lines.
- Planning: Identify relocation points that optimize performance,
ensure ease of maintenance, and meet structural load requirements on the
new location.
Execution:
- Safe Removal: Use tilt tables and dedicated hoisting equipment to
lower the AC units from higher floors.
- Relocation and Reinstallation: Reinstall the AC units, reconnecting all utilities and
verifying that mounting structures are secure.
- Commissioning: Test system performance, recalibrate control settings,
and document operational parameters.
E. Fire Door Installation
Preparation:
- Assessment: Determine the exact locations for new fire doors based
on fire safety audits and building layout reviews.
- Procurement: Source fire-rated doors and hardware that comply with
local fire regulations.
Execution:
- Installation: Remove any non-compliant door systems and install new
fire doors with precise alignment. Ensure door frames are properly
integrated into the building structure and that all sealing and closing
mechanisms function flawlessly.
- Verification: Test for proper operation, sound fire rating
certification, and accessibility for emergency evacuations.
F. Weather Coat & Painting Works
Preparation:
- Surface Cleaning: Thoroughly clean the exterior surfaces to remove all
contaminants, loose paint, and other residues using power washing or
sandblasting as needed.
- Surface Repair: Address minor defects (cracks, spalling) prior to
coating application.
Execution:
- Priming and Coating: Apply a high-performance primer followed by a weather
coat to ensure enhanced durability. Once cured, proceed with the final
paint layers using either spray techniques for uniformity across large
areas or roller/brush methods for detailed sections.
- Environmental Considerations: Monitor weather conditions (wind, humidity) to ensure
optimal application and curing times, especially in a high-rise context.
5. Coordination, Quality Control, and Handover
Inter-Trade
Coordination:
- Schedule sequential handoffs
between demolition, renovation, and installation teams using collaborative
project management tools. Maintain shared progress logs and hold regular
coordination meetings.
Quality
Assurance:
- Inspections: Employ senior engineers to conduct inspections at
every stage—from dismantling through to final finishes.
- Documentation: Maintain robust records, including photographic
evidence, inspection reports, and safety audits.
Finalization:
- Conduct a comprehensive
walkthrough with the client and quality assurance personnel. Ensure all
debris is cleared, non-structural elements are reinstalled correctly, and
finalize the documentation for project handover.
6. Example Task Sequencing and Timeline
|
Task |
Description |
Equipment/Resources |
Estimated
Duration |
|
Site
Mobilization |
Set up scaffolds, safety nets, and
designated storage areas |
Scaffolds, hoists, PPE, and communication tools |
1–2 days |
|
Brick
Works Dismantling & Removal |
Mark, dismantle brick units and
safely collect/remove debris |
Pneumatic chisels, hoists, and dust
suppression systems |
3–5 days |
|
RCC Works
Dismantling |
Controlled saw cutting, removal of
RCC segments, and immediate shoring |
Concrete saws, bracing/shoring,
dust suppressors |
4–7 days |
|
Aluminium
Renovation |
Inspect, prepare, dismantle faulty
units, and reinstall new elements |
Hand tools, cleaning agents, and sealants |
2–4 days |
|
AC Unit
Relocation |
Disconnect, remove, and reinstall
air conditioners as per the new plan |
Tilt tables, hoists,
electrical/disconnect tools |
2–4 days |
|
Fire Door
Installation |
Remove old door sets, install new fire-rated
doors, and verify functionality |
Drills, fire-rated fixtures and
hardware |
1–2 days |
|
Weather
Coat & Painting Works |
Surface cleaning, priming, weather
coat application, and final painting |
Paint sprayers, rollers, scaffolds |
3–5 days |
|
Final
Inspection & Cleanup |
Quality audits, final handover
documentation, and site restoration |
Inspection checklists, waste
disposal tools |
1–2 days |
Final Thoughts
This
methodology embraces a well-organized, step-by-step approach—from initial
planning and mobilization through to detailed execution and final handover—to
guarantee that every facet of the project is addressed with maximum safety,
precision, and operational efficiency. By integrating advanced waste management
practices, stringent quality controls, and precise coordination among
specialized teams, WAZIPOINT SYSTEM
can successfully manage the high-rise project with minimal disruption and
high-quality outcomes.
PART_D
Below
is a detailed work methodology for WAZIPOINT
SYSTEM to execute the plumbing and water supply line works using uPVC and
CPVC pipes and fittings in a high-rise project spanning the 6th to 12th floors.
This methodology integrates precise installation procedures with robust
scaffolding and safety measures to ensure a seamless, efficient, and secure
operation.
1. Project Initiation and Planning
Scope
Definition:
- Plumbing and Water Supply
System:
- Materials: Use uPVC pipes for cold water and drainage systems,
and CPVC pipes where hot water or chemical resistance is required. All
installations will incorporate fittings such as elbows, tees, reducers,
couplings, and support hangers as indicated in the approved design
drawings.
- System Layout: Design and implement main lines, branch runs, and
ancillary components such as valves and filters to create a comprehensive
water supply network.
Pre-Planning
Activities:
- Document Review: Evaluate blueprints, plumbing schematics, and design
specifications to verify pipe sizes, flow rates, and junction details.
- Material Procurement: Source certified uPVC/CPVC pipes and approved fittings
along with adhesives and solvent welds specific to these materials.
- Team Coordination: Assemble an experienced team, including site
engineers, plumbing specialists, and safety officers, and schedule regular
coordination and progress meetings.
2. Site Preparation and Scaffolding Setup
Scaffolding
and Access:
- Scaffolding Design and
Erection:
- Erect temporary scaffolding
systems along the 6th to 12th floors ensuring that they are engineered to
handle both personnel and equipment.
- Install guardrails, toe
boards, and secure platform areas to provide a stable, secure working
environment.
- Safety Measures:
- Ensure all personnel are
equipped with fall-protection devices, such as harnesses and lanyards,
along with hard hats, gloves, and safety boots.
- Conduct daily inspections of
the scaffolding structures and access pathways, confirming stability and compliance
with local safety standards.
- Site Organization:
- Establish clearly marked work
zones and safe storage areas for tools and materials, minimizing
cross-traffic and potential hazards.
- Set up a communication network
(e.g., two-way radios) for constant updates between on-site teams and
supervisors.
3. Detailed Execution Methodology
A. Layout, Measurement, and Pre-Installation
- Pipe Routing and Marking:
- Review the approved plumbing
layout on-site, marking designated pipe runs on walls, ceilings, and floors.
- Verify that access and
alignment coincide with structural elements, ensuring seamless
integration with existing services.
- Material Preparation:
- Measure and cut uPVC and CPVC
pipes accurately using proper pipe-cutting tools.
- Prepare all fittings by ensuring
that socket surfaces are clean and free from debris, using recommended
solvent welds or adhesives for uPVC/CPVC as per manufacturer guidelines.
- Pipe Supports and Hangers:
- Pre-install supports, clamps,
and brackets at required intervals, ensuring that the weight of the pipes
and the pressure from water flow are adequately managed.
- Check that support
installations adhere to spacing norms and load requirements for high-rise
applications.
B. Installation of Plumbing Lines
- Fitting Installation:
- Connect pipes using solvent
welding techniques that guarantee strong, leak-proof joints.
- Ensure that all connections
are verified against the design details, with special attention to
changes in direction (elbows) and branch connections (tees).
- Securing Pipelines:
- Affix pipelines securely along
scaffolding-supported access, using pre-installed clamps and cable ties
as necessary.
- Continuously check levelness
and alignment during installation to avoid any undue bending or stress on
the pipes.
- Integration with Ancillary Components:
- Install valves, shut-off
controls, and any necessary water meters or filters in line with the
plumbing drawings.
- Where applicable, apply
insulation on CPVC sections transporting hot water to prevent heat loss
and ensure user safety.
C. Testing and Quality Assurance
- Hydrostatic Pressure Testing:
- Once the system is completely
installed, fill the pipelines with water and pressurize them to the
design specification.
- Monitor pressure gauges to
detect any potential leaks at joints or fittings and make corrective
repairs immediately.
- Final System Checks:
- Conduct visual inspections
from both the floor and the scaffolding levels to verify the integrity of
joints, supports, and the overall alignment of the pipelines.
- Document all test results and
provide a comprehensive quality report for compliance and future
maintenance reference.
4. Safety and Scaffolding Procedures
Pre-Work
Safety Briefings:
- Hold daily toolbox talks
emphasizing fall protection, proper tool handling, and emergency
evacuation routes.
- Reiterate the importance of
using personal protective equipment (PPE) and maintaining communication
protocols throughout the workday.
On-Site
Emergency Preparedness:
- Develop and display an
emergency response plan that includes rescue procedures from scaffolding
areas.
- Ensure that first aid kits are
accessible and that at least one trained first-aider is present during
high-risk operations.
Inspection
and Documentation:
- Record daily scaffolding and
work area inspections to maintain an audit trail of safety compliance.
- Use checklists to ensure that
every phase of the installation—from pipe cutting to final testing—meets
safety and quality standards.
5. Documentation, Handover, and Maintenance
Finalization:
- Compile detailed records
including installation logs, test reports, scaffolding inspection sheets,
and material certifications.
- Conduct a joint walkthrough
with the client and quality assurance teams, addressing any final
adjustments or recommendations.
Handover:
- Provide comprehensive system
documentation which includes layout drawings, material specifications, and
a recommended maintenance schedule.
- Offer training to building
facility management on the operational checks and troubleshooting
procedures for the plumbing system.
Example Installation Schedule
|
Task |
Description |
Duration |
Key
Equipment/Resources |
|
Scaffolding
Setup |
Erecting and verifying scaffolding
with safety gear |
1–2 days |
Scaffolds, PPE, guardrails, loss
prevention tools |
|
Pipe
Routing & Measurement |
Marking pipe paths and cutting
uPVC/CPVC pipes |
1–2 days |
Measuring tools, pipe cutter,
marking tools |
|
Fitting
and Assembly |
Solvent welding and connecting
pipes with proper fittings |
3–5 days |
Solvent weld adhesives, approved
fittings, and clamps |
|
Support
Installation |
Installing pipe hangers and
securing pipelines along scaffolding |
1–2 days |
Supports, clamps, cable ties, and leveling tools |
|
Hydrostatic
Testing |
System pressurization and leak
checks |
1–2 days |
Pressure gauges, water pump, test
equipment |
|
Final
Inspection & Handover |
Quality control, documentation,
and client walkthrough |
1 day |
Inspection checklists,
documentation tools |
Final Thoughts
This
methodology is designed not only to implement an efficient plumbing and water
supply system using uPVC and CPVC materials but also to ensure that work on a
high-rise building is executed safely. The integration of robust scaffolding
measures and strict safety protocols is vital in mitigating risks associated
with working at height. Regular supervision, testing, and detailed
documentation ensure that the final installation is reliable, compliant, and
built to last.
Beyond
the immediate installation, consider employing digital project management
platforms to monitor progress in real time and schedule periodic maintenance to
uphold system integrity over the years. This forward-thinking approach will
ensure both the safety of onsite personnel and the long-term performance of the
plumbing system.
PART_E
Below
is a comprehensive work methodology for WAZIPOINT
SYSTEM to execute dam proof work, plaster work, and weatherproofing of the
outdoor wall on a 6th to 12th floor building. This methodology is designed to
ensure durability, optimize material performance against moisture and weather
conditions, and uphold the highest standards of safety and quality at elevated
levels.
1. Project Initiation and Pre-Planning
Scope
Definition:
- Dam proof Work: Application of damp-proof coatings or membranes along
the exterior face to prevent moisture ingress. This may include using
specialized water-repellent compounds or continuous membranes that act as
barriers between the substrate and weather elements.
- Plaster Work: Providing a strong, even base layer on the outdoor
wall using a mix of cement, lime, and suitable aggregates. The plaster not
only offers aesthetic value but also acts as a substrate for the
subsequent weatherproof coating.
- Weatherproof Work: Applying a high-performance weather coat to protect
the plastered surface from rain, UV exposure, and temperature variations.
This layer typically involves a primer, followed by one or more coats of
weatherproof paint or sealant that offers both water repellency and enhanced
durability.
Pre-Planning
Activities:
- Document Review: Assess design drawings, substrate conditions, and
environmental factors. Verify material specifications and mixing ratios
for damproofing and plastering as well as manufacturer recommendations for
weatherproof coatings.
- Material Procurement: Source certified damproof compounds or membranes,
high-quality cement and lime-based plaster materials, and weatherproof
coatings that meet external environmental standards.
- Team Coordination & Safety
Planning: Assemble a specialized team
including site engineers, plastering experts, and safety officers. Develop
a comprehensive safety plan addressing the challenges of working on floors
6 through 12, with specific focus on scaffolding, PPE, and fall
protection.
2. Site Preparation and Scaffolding Setup
Scaffolding
and Access:
- Scaffolding Design and
Erection:
- Install scaffolding systems
that provide full and secure access to the outdoor wall from the 6th to
12th floors.
- Equip scaffolding with
guardrails, toe boards, secure platforms, and non-slip surfaces to ensure
fall protection.
- Safety Measures:
- Provide and enforce the use of
personal protective equipment (PPE) such as helmets, harnesses, gloves,
and safety boots.
- Conduct daily inspections of
scaffolding, access ladders, and other working platforms. Establish
exclusion zones to prevent access by unauthorized personnel.
Site
Organization:
- Clearly demarcate work zones,
materials storage areas, and zones for waste collection.
- Set up communication channels
(e.g., two-way radios) between team leaders, safety officers, and workers
for real-time coordination on the high-rise.
3. Detailed Execution Methodology
A. Damproof Work
Surface
Preparation:
- Cleaning: Thoroughly clean the exterior wall to remove dust,
loose particles, and any efflorescence. If required, lightly wash the
surface with water and allow complete drying.
- Repair: Address minor cracks or imperfections with a patching
compound to ensure a continuous, even substrate for the damproof material.
Application
of Damproofing Material:
- Selection: Use a damproof mortar or a liquid waterproofing
compound appropriate for high-rise exterior walls. In some cases, a
membrane system may be employed if specified.
- Application:
- Apply the damproof compound
uniformly using trowels or spray equipment as per the manufacturer’s
recommendations.
- Ensure special attention to
joints, corners, and areas of potential water collection.
- Allow adequate curing time so
that a continuous, impermeable barrier is formed.
B. Plaster Work
Substrate
Preparation:
- Confirm that the damproof layer
is fully cured.
- If necessary, apply a bonding
agent to enhance adhesion between the damproof layer and the plaster.
Mixing
and Application:
- Mix Design: Prepare the plaster mix (typically a blend of cement,
lime, and washed river sand) in proportions specified for external use.
Add water-repellent admixtures if mandated to enhance durability.
- Base Coat Application:
- Apply an initial rough coat
(approximately 10–12 mm thick) to establish a strong base.
- Use trowels or sprayers for
uniform application, ensuring the mix is well compacted to eliminate
voids.
- Finishing Coat:
- Once the base coat sets
sufficiently, apply a finishing coat (around 4–6 mm thick).
- Trowel the finish to achieve a
smooth surface that is primed for weatherproofing.
C. Weatherproof Work
Surface
Preparation:
- After plaster curing (typically
allowing 7–14 days depending on environmental conditions), inspect the
plaster surface for cracks, dust, or imperfections.
- Lightly sand or patch the
surface as needed to ensure an even substrate.
Application
of Weatherproof Coating:
- Priming: Apply an appropriate primer that enhances the adhesion
of the weatherproof coat and seals the plaster surface.
- Weatherproof Coating Layers:
- Using weather-resistant paint
or sealant, apply one or more coats as recommended by the product
guidelines.
- Ensure even application by
using rollers or spray equipment suited for high-rise external surfaces.
- Monitor environmental
conditions (wind, temperature, humidity) to ensure optimal drying and
curing.
Quality
and Curing:
- Allow proper drying time
between coats and after the final application.
- Inspect for uniformity, proper
film build, and absence of run-off or pooling.
- Document the layer thickness
and overall appearance according to quality control protocols.
4. Coordination, Quality Control, and Documentation
Inter-Trade
Coordination:
- Schedule sequential work:
complete the damproof and curing period before proceeding to plastering,
and similarly, finalize the plaster work prior to weatherproof coating.
- Hold regular coordination
meetings among trade teams and supervisors to discuss progress and address
challenges.
Quality
Assurance:
- Inspections: Conduct inspections at every stage—with engineers
verifying adhesion, thickness, and uniformity of the damproof layer, the
plaster, and the weatherproof coating.
- Documentation: Maintain detailed records of material batches, mixing
ratios, application methods, curing times, and final inspection results.
Final
Handover:
- Provide comprehensive handover
documentation comprising test results, photographic records of each stage,
and maintenance recommendations.
- Conduct a final client
walkthrough to confirm compliance with project specifications and quality
standards.
5.
Example Task Sequencing and Timeline
|
Task |
Description |
Equipment/Resources |
Estimated
Duration |
|
Scaffolding Setup & Safety |
Erection of scaffolds with full
fall protection and marked work zones |
Scaffolds, guardrails, PPE, and communication devices |
1–2 days |
|
Surface Preparation (Damproof) |
Cleaning, patching, and priming
the wall surface for damproof material |
Brushes, cleaning agents, and patching
compounds |
1 day |
|
Damproof Application |
Uniform application of damproof
compound/membrane across the wall |
Trowels, spray equipment, and specialized
waterproofing products |
1–2 days |
|
Plaster Base & Finishing Coat |
Mixing and applying base and
finishing plaster layers |
Mixing tools, trowels, and bonding
agents |
3–4 days |
|
Weatherproof Coating |
Primer and weather-resistant paint
application |
Rollers/sprayers, primers,
weatherproof coating |
2–3 days |
|
Quality Inspection & Handover |
Final visual inspections,
thickness checks, documentation, and client walkthrough |
Inspection checklists,
documentation tools |
1 day |
Final Thoughts
This
methodology not only establishes clear step-by-step procedures—from damproof
application through plastering to final weatherproof coating—but it also
emphasizes the importance of robust scaffolding, rigorous safety protocols, and
structured quality control on a high-rise project. Integrating these practices
ensures that the outdoor wall performs reliably against moisture and weather
extremes and contributes significantly to the building’s longevity and
appearance.
In
addition to the core steps outlined, WAZIPOINT
SYSTEM may consider employing digital monitoring tools for real-time
quality assessments, exploring innovative damproof products for enhanced
sustainability, and scheduling routine maintenance inspections to prolong the
service life of these treatments.
No comments:
Post a Comment
WAZIPOINT:
Thank you very much to visit and valuable comments on this blog post. Keep in touch for next and new article. Share your friends and well-wisher, share your idea to worldwide.