VRF Shifting Contract Between WAZIPOINT and Dhaka Chamber of Commerce and Industry, Technical issues, Safety issues, running office hours,
VRF shifting contract — scope and priorities
Below is a concise, ready-to-adapt contract framework and operational checklist for a VRF (Variable Refrigerant Flow) system relocation between WAZIPOINT (contractor) and Dhaka Chamber of Commerce and Industry (client). It covers the scope of work, technical requirements, safety obligations, running office hours/working schedule, testing & handover, and contractual protections.
1. Scope of Work (detailed)
- Survey & pre-mobilization: Site survey, as-built drawings, load verification, and written relocation plan.
- Dismantling: Safe removal of indoor and outdoor units, refrigerant recovery to certified cylinders, and labeling of all components.
- Transport & storage: Secure transport; climate-controlled storage if required.
- Reinstallation: Re-mounting units, piping, insulation, electrical reconnections, control integration, and commissioning.
- Testing & commissioning: Pressure/leak tests, vacuuming, refrigerant charging, electrical safety tests, control calibration, and performance verification under load.
- Technical references: follow manufacturer installation guides and VRF method statements for safe, code-compliant work.
- Technical references: follow manufacturer installation guides and VRF method statements for safe, code-compliant work.
2. Technical requirements & deliverables
- Design verification: Confirm capacity, line lengths, oil traps, and elevation differences; update piping schematic.
- Refrigerant handling: Use certified recovery equipment; record refrigerant quantities and certificates.
- Electrical: Provide single-line diagrams, ensure proper breakers, earthing, and overload protection.
- Controls & BMS: Preserve or reconfigure building management interfaces; test all thermostats and communication lines.
- Documentation deliverables: As-built drawings, commissioning report, refrigerant log, test certificates, and operation manuals.
- Standards: Commissioning and design should align with VRF installation best practices and ASHRAE guidance.
- Standards: Commissioning and design should align with VRF installation best practices and ASHRAE guidance.
3. Safety obligations (contract clauses & site rules)
- Primary duty: Contractor is responsible for site H&S and must comply with local regulations and the client’s site safety rules.
- Mandatory items: Toolbox talks, PPE for all personnel, hot-work permits, electrical isolation procedures, fall protection, and safe lifting plans.
- Refrigerant risk controls: Leak detection, ventilation for enclosed spaces, and an emergency response plan for refrigerant exposure.
- Permit-to-work: All high-risk tasks require written permits signed by the client representative.
- Incident reporting: Immediate notification of any incident; contractor to investigate and submit a corrective action plan.
- Best practice reference: Use a formal method statement and health & safety plan for VRF works.
- Best practice reference: Use a formal method statement and health & safety plan for VRF works.
4. Running office hours and working schedule
- Normal office hours: Define standard hours (e.g., 09:00–17:30). Routine, non-disruptive tasks to be scheduled within these hours.
- After-hours/disruptive work: Noisy, vibration, or power-isolation tasks to be scheduled outside office hours (e.g., 20:00–06:00) with prior 72-hour notice.
- Access & security: Contractor personnel must sign in/out; provide ID badges; the client must provide an escort if required.
- Daily coordination: Daily progress brief (15 minutes) at shift start with client representative; maintain a daily log of activities and any deviations.
- Emergency work: Define response window (e.g., contractor onsite within 2 hours for critical failures) and billing/compensation terms.
5. Testing, acceptance, and handover
- Pre-commissioning checks: Mechanical integrity, insulation, electrical continuity, and vacuum levels.
- Commissioning tests: Run units under design load; measure supply/return temperatures, superheat/subcooling, and power draw.
- Acceptance criteria: System meets specified cooling capacity within ±10% and operates stably for a continuous 4-hour run without alarms.
- Punch-list & rectification: Client issues punch-list; contractor to rectify within agreed SLA (e.g., 7 calendar days).
- Final handover: Handover package including test reports, warranties, and training session for facility staff.
6. Contractual protections, insurance & commercial terms
- Milestones & payments: Mobilization, dismantling complete, reinstallation complete, commissioning complete (each tied to % payment).
- Retention: Holdback (e.g., 5–10%) until successful handover and expiry of the initial defect liability period.
- Liquidated damages: Daily rate for unjustified delay beyond the agreed completion date.
- Insurance: Contractor to maintain public liability, employer’s liability, and equipment transit insurance; provide certificates before mobilization.
- Warranties: Minimum 12 months workmanship warranty plus manufacturer warranties; define remedies for defects.
- Change control: Written change orders are required for scope changes, with cost and time impacts documented.
7. Sample clause snippets (copy-ready)
Scope: “Contractor shall dismantle, transport, reinstall, and commission the VRF system as per the attached relocation plan and manufacturer guidelines. All refrigerant shall be recovered and handled by certified personnel.” Safety: “Contractor shall submit a site-specific Health & Safety Plan and Method Statement 7 days prior to mobilization. All work requires a permit-to-work for hot works and electrical isolation.” Working hours: “Normal working hours are 09:00–17:30. Disruptive activities shall be scheduled between 20:00–06:00 with 72 hours’ notice.” Acceptance: “Final acceptance upon successful commissioning tests and delivery of as-built documentation; client may withhold retention until defects are closed.”
8. Practical next steps and clarifying questions
Recommended next steps
- Approve the scope and working hours in writing.
- Contractor to submit: detailed relocation plan, method statement, H&S plan, and schedule.
- Client to confirm access, security, and any building-specific constraints.
- Agree on milestones, payment schedule, and insurance certificates.
Clarifying questions for finalizing the contract
- Exact system details: model numbers, refrigerant type, and total indoor/outdoor unit counts.
- Preferred normal and after-hours windows and any blackout dates.
- Any BMS integration constraints or third-party vendors to coordinate with?
- Site-specific safety rules or permit processes unique to DCCI premises.
No comments:
Post a Comment
WAZIPOINT:
Thank you very much to visit and valuable comments on this blog post. Keep in touch for next and new article. Share your friends and well-wisher, share your idea to worldwide.