PAINTING AND CLEANING ROUTE FOR A CONTRACT

Painting and Color Combination
Fig-Color of Various Carpet

The Adequate Painting and Cleaning Plan for Erection Contract

The requirements of this article on painting and cleaning schedules of a contract should be interpreted in accordance with the requirements and recommendations of standard BS 5493 and CP 231, CP 3012 and the paint manufacturer’s special instructions where applicable.


Color selection should be in accordance with BS 1710 and BS 4800 or equivalent material standards.

The Paint Supplier Selection

Immediately following the award of a Contract, the Service provider should submit the names of the proposed paint supplier and applicator together with a quality assurance program for approval. 

All paints for a contract should be provided by one manufacturer and preferably should be manufactured in one country to ensure compatibility

Schedule and Service Life for Painting Work

The painting of the plant should be carried out in accordance with the appropriate schedule. 

The work is generally covered by the schedules but where particular items are not referred to specifically, they should be treated in a manner similar to other comparable items as agreed with the Engineer.

The schedule indicate standards of surface preparation and painting which is intended to give a minimum service life of 10 years in a coastal industrial environment, with need for minor remedial work only during the intervening period.

How Ensure Painting Standard

Steel sections and plate should be free from surface flaws and laminations prior to blast cleaning and should not be in worse condition than Pictorial Standard B, Swedish Standard SIS 05 5900.

Sponsored:

The Engineer is prepared to consider alternative paint schemes to meet the requirements of fabrication using modern automated materials handling systems, provided they offer the same standards of surface protection and service life as those intended by the schedules.

All coating proposed for the internal protection of domestic water storage tanks and Employer sanitation plants should be certified by an approved independent Authority as suitable for use in potable water installations and should meet the non-painting requirements of BS 3416.

The Painting and Cleaning Procedure

All paints should be applied by brush or spray in accordance with the schedule, except for priming coats for steel floors, galleries and stairways where dipping is permitted.

Where paint is to be applied by spray, the applicator should demonstrate that the spray technique employed does not produce paint films containing vacuoles.

Where paint coatings are proposed for the protection of surfaces of equipment exposed to corrosive conditions, such as plant items exposed to brines or sea water immersion in liquid, or wet gases, the coatings should be formulated to the suitably corrosion resistant and should be high voltage spark tested at works and/or at site prior to commissioning.

High Voltage Direct Current Test Procedure for Painting

The test procedure should be based on the use of a high voltage direct current. The voltage used should be 75% of the breakdown voltage of the coating. This breakdown voltage should first be separately determined using test plates coated with the specified coating formulation and thickness. 

The coating on the test plate should also be micro-sectioned by the applicator to show that it is free from vacuoles and other defects likely to invalidate the test procedure.
If the defects revealed by the above test procedure do not exceed one per 5m2 of coating surface, the coating need not be re-tested after the defects have been repaired. If the defects exceed one per 5 m2 of coating surface, the repairs should be resettled after any curing is completed, and this procedure should be repeated until the defects are less than one per 5 m2 of coating surface. After repair of these defects, the equipment can be placed in service without further testing.

Especial Consideration for Painting and Cleaning

Weather Condition: Painting should not be carried out under adverse weather conditions, such as low temperature (below 40oC) or above 90% relative humidity or during rain or fog, or when the surfaces are less than 30oC above dew point, except to the approval of the Engineer or his duly appointed representative.

Dew Linger Point: On sheltered or unventilated horizontal surfaces on which dew may linger more protection is needed and to achieve this additional top coat of paint should be applied.

Damp & Condensation: Paint should not be applied to surfaces which are superficially or structurally damp and condensation must be absent before the application of each coat.

Sheet & Bright Parts: All plain sheet and bright parts should be coated with grease, oil or other approved rust preventive before dispatch and during erection and this coating should be cleaned off and the parts polished before being handed over.

Joint Part: Where lapped or butted joints form part of an assembly which is assembled or part assembled prior to final painting, the jointed surfaces should be cleaned free from all scales, loose rust, dirt and grease and given one brush applied coat of zinc phosphate primer before assembly.

Paint Film Thickness: All paint film thickness quoted are minimum and refer to the dry film condition. All thickness should be determined by the correct use of approved commercial paint film thickness measuring meters.

Bolt & Timber Painting: Structural bolts should be galvanized, sherardized or cadmium plated and painted as for adjacent steelwork.
All structural timber like timber joists, flooring, etc. not require to be painted and should be treated with two coats exterior grade approved timber preservative.

Sponsored:

Adequate Permission for Painting and Cleaning

Priming coats of paint should not be applied until the surfaces have been inspected and preparatory work has been approved by the Engineer or his duly appointed representative.

No consecutive coats of paint, except in the case of white, should be of the same shade. Thinners should not be used except with the written agreement of the Engineer.

The schedules differentiate between Treatment at Maker’s Works and Treatment at Site after Completion of Erection but the locations at which different stages of the treatments are carried out may be modified always providing that each change is specifically agreed to by the Engineer and the painting is finished at Site to the Engineer’s satisfaction.

The Service provider should ensure that precautions are taken in packing and crating to avoid damage to the protective treatment applied before shipment, during transport to the site.

Wednesday, January 20, 2016

CIVIL WORKS OVERSEE: MATERIALS AND WORKMANSHIP

This article described in brief on service provider obligation on materials and workmanship of civil work to execute an underground power transmission cable project.

How See Standards and Samples

All materials should  be the best quality of the respective kings specified or described in the Specification and Drawings and should  comply in all respects with the latest edition or amendment of the relevant British Standard except and insofar as that Standard is amended by this specification or Drawings.

WHAT IS THE TOLERANCE SCALE

The Works are to be constructed to lines, levels graded and dimension set out in the Drawing and it is hardly obligation for service provider to no make any departing from these lines, levels, grade and dimensions unless authorize  agree by the Engineer.

Importance of Samples to Project Oversee

Sponsored:
Test to identify PVC & XLPE
Samples of materials and workmanship which is proposed to employ in the execution of the works should be submitted with the detail to the Engineer for his approval.

Should any material or workmanship be employed which do not correspond in quality and character with samples the Engineer may at his discretion order their replacement on the Service provider’s responsibility.

For Example:

To predict corrosion level for underground cable and others metallic outdoor structure that would erect under scope of project, the soil sample should collect and send to engineer for laboratory analysis and take necessary action plan for future.

The amount of sample soil not less than 250g, sealed and plastic container with details location levels must be ensured.


MATERIALS TESTING OBLIGATION

The testing of cement, concrete, brick, soil samples or other materials as required in connection with the construction of the Works should be carried out in laboratories approved by the Engineer. The Service provider should pay all costs incurred in making, transporting, testing and providing equipment for the testing of materials.


HOW KEEP WORK FREE FROM WATER

The service provider  should  keep his Works free from water so that all the work may be carried out in the dry and he should  construct any temporary dams, water courses and other Works and provide operate and maintain pumps as may be necessary for this purpose, all at his own expense.

SOIL DISPOSAL OBLIGATION ON SITE


Soil Disposal in Site Work
Typical Cable Trench
Throughout the period of construction of the Works the Service provider should maintain the whole area of his operation in a clean, tidy and safe condition by arranging his materials in an orderly manner. 

All rubbish, waste materials, spoil, debris etc. should  be systematically cleared off the working areas as it accumulated and should  be deposited at connection points allocated by the Engineer and removal from site by the Service provider  at his own expense.

No mining or quarrying right are included in this Contact, but surplus soil may be sold by the Service provider after agreement with the Engineer that the employer has no use for that soil. 

Access must be maintained during trenching works and removal, and return of soil from and to site to allow for this is deemed to be included in the excavation rates.

Sponsored:

Friday, January 1, 2016

HOW TO ADD DOWNLOAD BUTTON IN BLOG POST

We as a Blogger know, free blogging platform provides a little bit limited tools to compose the blog post. But in this like and sharing age, we want to give and take unlimited, in online every day. That’s way today we need to be customized to present more attaractive and useful blogging stuff getting further visitors conversation.

If you are seeking a Download button to add in your blog post, to share some documents- like images, pdf or other formatted file that will give single click download provision. Then you have reached in the right place. WAZIPOINT will show you step by step, how to add a download button in your blog post whereas you like.

Sponsored:

How to Add Download Button in Blog-Post Step by Step

Just following few steps below, you can get able to add Download button in your blog post easily. Oky, let’s move__
Step-1
Go to Blogger Dashboard > Template;
First of all log in your blog account and go to blogger dashboard, as shown in red circle in figure below.
Blogger Template in Dashboard
Step-2
Backup your Template before making any changes to your blog;
It’s better to take backup before any change in HTML code. Just clicking the Backup/Restore button at top-right corner in your window and following the instruction you can do this, as shown in figure below. 
Blogger Template Backup & Restore
Step-3
Click on Edit HTML ;
Make change your HTML code, just clicking on Edit HTML button you can get the HTML code window.
Blogger Template
Step-4
Press Ctrl + F and search the code “]]></b:skin>”;
When window with HTML code appear to you after following step-3, just click on anywhere on HTML code area to place window cursor. Then a search box like below figure will appear, type the code ]]></b:skin>” into the sesrch box and hit enter button on your key pad; check the difference “typed code will appear as highlighted” as shown in figure in step-5.
Sponsored:

Blogger Template Search
Step-5
Now add the below  code just Above/Before ]]></b:skin>;
Blogger Template Code Search
Copy the below code and paste just above the code that highlighted as in above figure:
.downloadbutton {margin:20px auto;padding:20px 0;width:200px;}
.downloadbutton a {background:#fff;;color:#666;display:block;font-size:17px;font-weight:700;
font-family:'Arial',Verdana,sans-serif;height:50px;line-height:50px;text-align:center;
text-decoration:none;text-transform:uppercase;width:200px;position:relative;z-index:2;}
.downloadbutton a:hover {background:#ddd;}
.downloadbutton a:before {content:"\f019";font-family:FontAwesome;font-weight:normal;
padding:8px;margin-left:-12px;margin-right:6px;}
.downloadbutton span {background:#444;color:#fff;display:block;font-size:12px;font-family:'Arial', Verdana,sans-serif;height:40px;line-height:40px;text-align:center;width:200px;z-index:1;text-transform:uppercase;
font-weight:bold;}
.downloadbutton .up {background:#8493A0;margin:-25px auto;opacity:0;border-radius:0 0 5px 5px;transform: translate(0,-50px);transition:350ms;}
.downloadbutton .down {margin:-30px auto;opacity:0;border-radius:5px 5px 0 0;transform: translate(0,-50px);transition:350ms;}
.downloadbutton .down:before {content:"\f14a";font-family:FontAwesome;font-weight:normal;
margin-right:6px;color:#aaa;}
.downloadbutton:hover .up {opacity:1;transform: translate(0,0);}
.downloadbutton:hover .down {opacity:1;transform: translate(0,-90px);}
.demobutton {margin:20px auto;padding:20px 0;width:200px;}


Step-6
Clicl Save template;
Save Blogger Template
After paste the above code, save the changed hitting in as above  and come out from the window. Your blog is now ready to add Download button at anywhere in any post.

How Put Download Button & Link in Blog Post

When your blog is ready to add Download button, go to write a new post or edit an existing post.
Download Link Code
Go to HTML code mode just clicking on HTML as shown in figure. Select the exact location where you want to add the button “DOWNLOAD”, paste the below code there.
<div class="downloadbutton">
<a href="http://wazipoint.blogspot.com/2015/12/wazipoint-photo.html" rel="nofollow" target="_blank">DOWNLOAD</a>
<br />
<span class="up">Download Section</span>
<br />
<span class="down">Click Here</span>
</div>


NOTE: You must change the URL “http://wazipoint.blogspot.com/2015/12/wazipoint-photo.html” by your own targeted URL which file you do want to link as download.
You also can change red marked text by your own that will be visible in your post.
If you want download the pdf copy of this article, get from following download link:
DOWNLOAD
This is test download link for you
Click for test
Hope this will be helpful for your happy blogging and happy downloading! If you think it is helpful for others, then help them sharing it in any social network and enrich your network.

Saturday, December 12, 2015

FINALLY UNVEILED THE ULTIMATE SECRECY OF PAGE RANK IMPROVEMENT FOR BLOG

How Unveil Ultimate Secrecy of Page Ranking

How You Unveil The Ultimate Secret Point To Improve the Page Rank Of Your Blog? 

get more traffic and your blog post will be hit by more visitorsBlogger, everyone desires to get a high page rank for his blog; a high page rank means Google includes all search engines like your website and makes it visible to much more visitors.  Ultimately, you will get more traffic and your blog post will be hit by more visitors.

Before unveiling the secrecy to get a high page rank for a blog, we would like to discuss the king rules of page rank for a blog or website. If we don’t know the scope or pre-condition of page rank for a website, may our work will go astray.


Some website contains huge potential to get good page rank, but not getting in just time due to lack of proper SEO (Search  Engine Optimization). Oppositely any website can not get a high page rank if does not contain quality content.

King Rules To Improve  Page Rank For Blog 

Before going to the king rules to improving the page rank of your Blog, remember-

“Don’t follow any model blindly, Be a model;
Someone may follow you”
You may see huge suggestions, lots of advertisements, and so many ways to get a high page rank instantly on your Blog. Yes, there are many ways to improve website page rank and that grows step by step; remember that’s not happened over a night! Also remember, one rule may work for me, but may not for you. So, you need your own study to find out the way to improve your website page rank; but there are some fundamental rules that work for all.


We already mentioned making quality content; yes, this is the first king rule. Without enough text content, you can not get a good page rank for your Blog.


Google will be your good friend and remember your blog to display in front of more visitors if you put a lot of unique informatics text that actually visitors are searching for. 


The second king rule for your Blog page rank is SEO (Search Engine Optimization) or search engine friendly blog. Actually, there is no shortcut way to optimize the blog for a good page rank. There are lots of factors to improve the page rank of a website.


This single post is not enough to describe the all factors that optimize the page rank. My personal opinion is that if we follow all the rules to optimize our posts for search engines then the article will be for the machine, not for humans! So,  here we will focus on some common and basic rules, but we will advise you to research yourself on your Blog which will help you to unveil the real page ranking factors.

Sponsored:



What Technology Google Likes to Improve Page Ranking



Google including all other search engines have no time to read all of your content. You need to show Google some keywords from your post, Google just verifies your content and indexes to further remember.


Indexing your page, Google technology ultimately considers the following key points-


The page title and keywords;

Meta description of the page;

Contents text on pages ;

Link to other sources etc.


These points are very important to page ranking because Google has no time to scan all the page contents each searching time, Google just indexes the search keywords from these points and prioritizes relevant search contents.


When any user search for any content from any corner of the internet world, Google Spider search and compare the search keyword with each webpage and make visible to the user those pages which contain more relevant content. This happens within a few mili-seconds for Google.


The page title contains the most important keywords which actually means the contents of the pages shortly. The length of the page title will neither be very short, nor long. The standard length should be within 80 characters. Too long a page title may consider spamming!


Keywords and keyword phrases are important to page ranking, Google will not scan all the documents if find not any search keywords. First of all, Google searches the search keywords at the page title, and at the meta tag then consider source links. Ex- if you writing a post about cat food, the cat is the keyword. You should mention the word ‘cat’ in the page title, sub-title, post text contents, and in the meta tag; then your post will be visible when someone searches for cat-related something.


Meta Description, Google actually does not index meta keywords, it index meta description tag. The meta description should contain the most important search keywords. Meta description length should not excide 150 characters. More long or short and duplicate meta descriptions are shown as an error in webmaster tools.


Contents text on pages should contain the most relevant search keywords. Important keywords should contain in once H1 header, in multiple sub-header, minor-header, and body text.


Link to other sources on external or internal pages is very important to page ranking. Google values the sources of data and links to other pages. Backlink plays vital roles to earn a high page rank, we will discuss latter about backlink in this article.

How Open The Secret Door To Improve Blog Page Rank

Before we said there is no shortcut way to improve your Blog page rank, you should study and find out which step working for your blog. Now we will focus on some common ways that are helpful and proven to improve the page rank. We hope it will be helpful to you in opening the secrecy of your Blog page rank.

Quality and Unique Contents

We are repeating again, without improving the quality of your content you can not imagine the improved page rank for your Blog. Blog content must be good quality and unique. Yes, unique, you can not copy-paste the documents from others. Your content should have a unique special character. Original and useful content can give you a high page rank because visitors like useful content and Google likes to give a high page rank to the most visited page.

Keep in touch updating the website regularly

If you do not update your blog for a long time, your page rank may drop down. Every week you need to update and include some new content in your Blog, more frequently is better. Also, remember the contents you are putting, should match the described keywords, which will help to come back visitors and stay what Google also loves.

Optimize page contents

You posted quality writing on your pages, but may not be visible at the right time in the right place if your page is not optimized properly. The best way to optimize your content for conversational search, keep your post title with the most popular search keywords. Off course, the body contents of the article should fulfill the search query. Remember, over-optimization may cause for de-ranking of your page.

Image Optimize

Using ALT text on images, you can optimize and make Google searchable images. Google is blind and can not read the image, You need to introduce using some descriptive text in the “Alt text” box and give a suitable file name for the image.

Buildup a quality backlink

Google Like gives you a high page rank when to see visitors coming to your site from another site. Linking with other high page ranked sites you can improve your page rank easily. By sharing content,  adding links, and commenting on other blogs, you can buildup backlinks.

Sharing Contents

By sharing your blog content you can reach others very easily and firstly. Share your Blog by creating a site map, creating an RSS feed, translating your blog contents to other languages, sharing in many social networks, and sharing to other blogs there are so many ways to share. Also provide facilities to visitors to share their post with others easily, adding some social network buttons like Facebook, Google +, Twitter, LinkedIn, tumbler, Digg, Delicious, Diigo, StumbleUpon, Instapaper, Evernote, Pocket, Pinterest, etc.

Sponsored:



Backlink Ultimately Improve the Blog Page Rank

Good quality backlinks mean other sites pursuing Google that your blog content is useful which Google appreciates to give you a high page rank. Ultimately huge quality backlinks alone can reach your Blog to a high page rank.

If you search on the net you will get 100 ways, maybe 200 ways to get backlinks. We are not going into more details, just chalking out some important link-building methods that are very simple and easy to all-


Introduce your blog to others' blogs by sharing, commenting, joining the dialogue, asking questions, giving suggestions, and many more conversations;


Submitting the blog URL to different search directories like Google, Yahoo, Bing, AOL, etc, you can earn huge benefits, especially if you are a new blogger. Search engine technology will find your blog easily. There are also many more directories where you can submit your website URL and ensure as much as you know;


Share Your Blog with Blogging Community and other social networks and introduce as much as possible, linking will come gradually;


Write your post targeting the audience and study their search choice list, include researched keywords in your post, hit and link will come organically;


Be transparent on your blog; keep your blog fresh and clean, man and machine will love it. Ultimate secrecy will unveil automatically which will improve page rank from higher to the highest.


Friday, November 27, 2015

DRAWINGS DIAGRAMS AND CALCULATIONS FOR UNDERGROUND CABLE PROJECT

General Requirements And Importance Of Drawings-Diagrams For Underground Power Cable Project

The employer may engaged or contract with service-provider to execute an underground power cable project, service-provider actually carry out the whole works as per employer requirements. Here in this article we would like to focus on general requirements and importance of various drawings, designs and calculation sheet to execute an underground power cable project.

The term “drawing” should also included here diagrams, schedules, performance curves, and calculations etc. required for the comprehensive design of the works. The Service Provider should be responsible for the provision of all drawings required for the various stages of the Contract to execute the project.

All drawings, apart from workshop drawings, should be submitted to the nominated Engineer for his approval, in accordance with an approved program. 

The Service Provider should ensure that drawings are submitted for approval in prior enough time such that they may be approved within the specified period by the Engineer, prior to manufacture or construction commencing. 

Further adequate time must be allowed by the Service Provider to permit any comments for revised or modification made by the Engineer to be incorporated.


Any works performed prior to approval of drawings by the Engineer will be entirely at the Service Provider’s own risk including any delays that may result from modifications being found to be necessary by the Engineer.

The numbers of drawings required and the method of issue should be mentioned  in flow diagrams to  specification that keep free from any confusion.

The Service Provider should be fully responsible for obtaining any drawing or data of existing plant and installations that he requires in order to carry out the works, and should also be responsible for verifying that any drawings of existing plant and installations are accurate.

The Service Provider should provide suitable drafting and other staff on site that he requires investigating and producing any drawings that he requires of existing equipment and installations in order to carry out the works.

Where existing installations have been modified or extended the Service Provider may  provide complete new sets of drawings. In this respect the Service Provider should provide drawings detailing both the existing and new works and may not limit the scope of the drawings to the new works only.

What Should be Format of Drawings and Calculation Sheet ?

Sponsored:


Drawings are to be submitted for approval on paper prints, folded to A4 size with the project title-block and drawing numbers clearly visible. Details of the project title-block must be as per prior specified by employer.



All drawings are to be submitted on A series paper to ISO/5457. The maximum size of drawings should be A1 except for site survey and layout drawings which may be submitted as A0 size sheets, if necessary, to accommodate details on a scale of 1:100. Single line diagrams and schematic drawings should preferably be on a maximum sheet size of A2. All dimensional drawings should be the following scales and detailed.
      • 1:1, 1:2, 1:5, 1:10 and factors of 10 thereof;
      • Drawings symbols should be in accordance with IEC 117.
      • All drawings are to be submitted in Auto Cad format in CDR Disk.
      • Drawing titles should clearly identify the specific function of the drawings and where appropriate the name of the site(s) to which the drawing applies.
Single Line Diagram for High Voltage Underground Power Cable Line
Cable Schematic Line Diagram

How Follow Drawing Numbering and Revisions?

The Service Provider should be responsible for adding the nominated Engineers drawing numbers to all drawings prior to submittal. Following award of the contract the Engineer and Service Provider will review the numbering system, familiarize with each other requirements, and agree on the numbering system to be applied.

Comprehensive cross-reference are to be included on drawings and the Service Provider should include the Engineer’s drawing number in the cross-references.

At each and every issue of a drawing the revision should be raised, and details given in revision boxes on the drawings. Comprehensive details of revisions are to be given and phrases such as “REVISED”, “UPDATED”, “MODIFIED” or similar are not acceptable.

Reference to any drawing in communications should include the Engineer’s drawing number.

Drawing Submittals and Approvals Procedure

The Service Provider should submit drawings for the plant and works for formal approval to the nominated Engineer. A program of drawing submittal should be agreed with the Service Provider following the contract award. 

Drawings issued in accordance with this program should take account of the time periods necessary for postage, and approved by the Engineer, to ensure that approved drawings are available prior to manufacture the materials for the project execute. For site construction works, “Construction Issues” drawings are to be available, on site, at least 21 days prior to the commencement of the works.Where appropriate the drawings should be accompanied by supporting calculations.

Following examination the Engineer should allocate a status on drawings. The subsequent action and distribution of drawings will depend on the status given by the Engineer as detailed below.

“Approved”, the details of the drawing have been checked by the Engineer and appear to comply with the requirements of the specification. Once approved the Service Provider should raise the revision to indicate Approved by the Engineer on Mark the drawing “Construction Issue” and distribute as per employer requirement that mentioned in contract.

“Approved Subject to Comment”. The drawing has been examined by the Engineer, and apart from the minor details can be considered Approved subject to the Service Provider making the amendments required by the Engineer. The Service Provider may issue the drawing as “Approved” as outlined above without resubmitting to the Engineer for formal approval, provided the corrections have been made as required. 

“Examined and Returned with Comments”. The drawing is considered to be revised by the Service Provider and immediately resubmitted to the Engineer for approval. 

“Examination not required”. The drawing not requiring approval by the Engineer has been examined by the Engineer. Examples of typical drawings of this nature are: equipment schedules and diagrams of connections. Drawings returned to the Service Provider of this status should be stamped “For information only” and “Construction Issue” and issued in the same manner as Approved drawings.

Approval of a drawing by the Engineer must in no way to relieve the Service Provider of his responsibilities under the Contract.

Service Provider may revise a drawing for any reason following approval by the Engineer, the revised drawing is to be resubmitted for re-approval by the Engineer, the original approval automatically being void.

The Service Provider must submit,  marked-up copies of the drawing issue programmed indicating the up to date status on drawing submittal and approval on a monthly basis. In addition the Service Provider should submit a schedule of the total number of drawing submitted, together with the total numbers of each of the above categories. An “S” curve is also to be submitted indicating the total number of planned approved drawing together with the actual numbers to date.

Sponsored:

As Built Recorded Drawing and Construction Amendment for Project

During construction of the Works on the site, the Service Provider should ensure that all departures, modifications and corrections to the approved drawings are recorded. All such changes to the drawings are to be marked in red to show on “as-built” stated and one set of “as-built” drawing are to be available on the site at all times.

If Service Provider wish to make modifications as per site requirement on the approved construction drawings which influence the operation of the Plant, he should obtain the approval of the Engineer’s representative prior to instituting the modifications.

Following examination of the “as-built” drawing the Engineer’s representative should return one copy to the Service Provider indicating approval of the construction modifications, or further modifications required to satisfy the requirements of the specifications.

Record Drawing for Cable Line Construction Project

On receipt of Approval of “as-built” drawings, the Service Provider  be responsible for the production of Record Drawings for the complete plant on each section of the Works.

The Service Provider should modify the revision to “As-Built” and “Record Drawing” for all drawings applicable to the section of the works and submit these for approval to the Engineer.

On receipt of the Engineer’s approval the Service Provider will provide sets of paper prints of each drawing as detailed on pre-specification of the contract. Any contract drawing included in the Operation and Maintenance manuals should also be revised in accordance with any “as-built” modifications and re-issued.

These sets of record drawings should be issued within 90 days of the Taking-over of the completed plant.

Sunday, November 22, 2015

DUAL COMPARTMENT OPTICAL TERMINATION BOX


CONTENTS



1.  GENERAL.......................................................................................................................3

1.1 Scope..............................................................................................................................3

2.  INTRODUCTION OF OTB.........................................................................................3

3.  OTB REQUIREMENTS..............................................................................................3

3.1 Description...................................................................................................................3

3.2 Drawings......................................................................................................................4

3.3 Dimension and Material Specifications......................................................................5

4.  Environmental PERFORMANCE……………………...................................................6

4.1 Vibration Test..............................................................................................................6

4.2 Thermal Cycling Test..................................................................................................6

4.3  Axial Pull-out Test......................................................................................................7

4.4  Water protection test (IP55) for Outdoor Type.........................................................7

5.  PACKING & MARKING...................................................................................8

5.1 Packing........................................................................................................................8

5.2 Marking.......................................................................................................................8




1. GENERAL



1.1    Scope


This  internal specification includes the structure, characteristics and packing/marking information of FOTB-I/O-DC SERIES. The FOTB-I/O-DC SERIES is designed to provide many important functions in the FTTx Network such as the optical signal distribution, cable storage and fiber termination/splicing. The FOTB-I/O-DC SERIES shall be produced by the ISO-9001 certified production facilities. And all processes from product design to packaging were controlled by the Quality-Control System.





Model

Description

FOTB-I/O-DC SERIES

FOTB: Optical Termination Box

I/: Indoor/Outdoor installation

DC: Dual Compartment



2. INTRODUCTION of OTB



LS Optical Termination Box is designed to terminate, splice and interconnect fiber optic cables in an outdoor environment. This box accommodates FTTH applications by mounting to the exterior surface of a dwelling and connecting between the distribution cable and drops routed to individual living units.



3. OTB REQUIREMENTS



3.1    Description



The box is divided into two sections with distribution cable routed into one section and drop cable routed into the other section. The cables meet at a splicing field that includes termination for the distribution cable and parking for the drop cables or the splice field that can be configured with splice trays for splicing the cable. The box may be pre-terminated on the distribution side with an outside plant cable stub so that the unit is quickly connected to the plant. It may be pre-wired with pigtails on the drop side so that individual drops routed into the unit can be spliced to the connectorized pigtails.



clip_image004[10]

<Fig. 1. Photo of FOTB-DC Series>



3.2   Drawings

clip_image002[12]

<Fig. 2. Ref. Drawings of FOTB-I/O-DC SERIES>



3.3    Dimension and Material Specifications

-        Indoor


Parameter

12FO

24FO

36FO

48FO

General

Dimension

(LXWxH)(mm)

350x320x80

350x320x80

350x320x125

350x320x150

Color

Ivory / Beige / Black

Material

SPCC

Cable Entry

No. of Entry (In/Out)

2 / 2

Dia. of Inlet (mm)

Max. 25

Dia. of Outlet (mm)

Max. 25

Adaptor*)

Type

SC(Default) / LC / FC

No. of Adaptor

Max. 12

Max. 24

Max. 36

Max 48

Connection

Splice Method

Fusion / Adaptor

No. of splice tray

1

2

3

4

Capacity per tray

Max. 12

Total Capacity

Max. 12

Max. 24

Max. 36

Max. 48

Application

Installation Environment

Indoor

Installation type

STD: Wall mount(Option for Pole mount)

Locking Method

Key Lock

* Adaptor panel type can be substituted other type which can accommodate Simplex LC, Duplex LC, Duplex SC adaptor and other types.



-        Outdoor


Parameter

12FO

24FO

36FO

48FO

General

Dimension (LXWxH)(mm)

350x320x100

350x320x100

350x320x150

350x320x170

Color

Ivory / Beige / Black

Material

Aluminum (or Stainless Steel)

Cable Entry

No. of Entry (In/Out)

2 / 2

(or In case of drop entries: 12 / 24 / 36 / 48)

Dia. of Inlet (mm)

13 ~ 18

Dia. of Outlet (mm)

13 ~ 18(or In case of drop entries: 3 ~ 6)

Adaptor*)

Type

SC(Default) / LC / FC

No. of Adaptor

Max. 12

Max. 24

Max. 36

Max 48

Connection

Splice Method

Fusion / Adaptor

No. of splice tray

1

2

3

4

Capacity per tray

Max. 12

Total Capacity

Max. 12

Max. 24

Max. 36

Max. 48

Application

Installation Environment

Indoor

Installation type

STD: Wall mount(Option for Pole mount)

Grounding

Available

Locking Method

Key Lock

* Adaptor panel type can be substituted other type which can accommodate Simplex LC, Duplex LC, Duplex SC adaptor and other types.


4. ENVIRONMENTAL PERFORMANCE





4.1 Vibration test


Test Procedure


1.  Fix the fiber distribution panel on the vibration tester

2.  Vibrate for 1hours with amplitude 1mm, frequency 10-55-10Hz in 10minutes

3.  Check the mechanical damage

Requirements

There should be no cracks, fractures and disconnection.

Test Assembly
[Test Equipment]

Vibration Tester HI-5050 clip_image003










 


Test Result

1. Cracks/fracture/disconnection

None

2. Mechanical damage

None

Judgment

Complied



4.2 Thermal cycling test


Test Procedure

1.  Put fiber distribution panel in the tester.

2.  Thermal cycle: 20 2 50(relative humidity 80%) 20

    (Maintaining 2hr at each Temp.)

3.  Temp. rising/falling: 1 /min

4.  2 cycling test(17hr 12min)

5.  Check corrosion and mechanical damage.

Requirements

1.  There should be no corrosion

2.  There should be no mechanical damage.

Test Assembly

clip_image005

Test Result

1.Crossion

None

2. Mechanical damage

None

Judgment

Complied

4.3 Axial Pull-out Test

  


Test Procedure


1.    Load F= D x 1000N/45 (D: cable diameter)

2.    Longitudinal axis for 30 min

Requirements

No Pull-out of cables from the enclosure

Test Assembly

    




 clip_image002[14]






        

Test Result

1. Cable pull-out

None

2. Mechanical damage

None

Judgment

Complied

Remark

-



4.4 Water protection test (IP55) for Outdoor Type





Test Procedures

The board is tested by means of a spray head or a flushing pipe which is aimed at it from all sides according to the standardized testing time / volume flow.

Requirements.

Water Penetration

Test Assemble


















Capture




 


Test Result

Water Penetration

None

Judgment

Pass

Remark





5. PACKING AND MARKING



5.1 Packing

5.1.1 The LS FOTB-I/O-DC SERIES shall be well packed in individual box.

5.1.2 The LS FOTB-I/O-DC SERIES shall have necessary accessory for installation, I.e. user manual etc.

5.1.3 Each LS FOTB-I/O-DC SERIES is to be packed with a protective material.



5.2 Marking

Details given below shall be distinctly marked with a weather proof material on the both outer sides of the shipping carton. Other shipping mark is also available if requested by customer.



-      Product item

-      Country of origin

-      Manufacturer’s name and/or trademark

-      Gross weight

-      Caution mark, I.e. maximum stacking height





<The end of specification>