| Fiber Cable Installation Project |
Project announcement — WAZIPOINT SYSTEM awarded Optical Fiber Cable Installation by Dhaka Electric Supply Company PLC (DESCO).
Project title: Optical Fiber Cable Installation for DESCO.
Client: Dhaka Electric Supply Company (DESCO).
Contractor: WAZIPOINT SYSTEM
Scope (summary): Duct pipe laying; optical fiber cable blowing; handhole construction (1200 × 1100 × 1075 mm) with materials; supply, transport, and laying of 100 mm PVC pipe for road crossings; transportation of materials from DESCO store to site.
Start: To be confirmed with DESCO.Status: Contract awarded.
Key highlights
- Turnkey civil and fiber works covering duct installation, cable blowing, and handhole construction.
- Road-crossing solution using 100 mm PVC conduits to protect fiber and meet traffic safety requirements.
- Logistics included — materials transported from the DESCO store to the site under the contractor's responsibility.
- As-built deliverables and test reports to be handed over on completion.
Technical execution plan (concise)
1. Assumptions and scope boundary
- Work limited to items listed by DESCO: duct laying, cable blowing, handholes (specified size), 100 mm PVC road crossings, and transportation from the DESCO store.
- Permits, traffic management approvals, and utility clearances to be obtained before civil works start.
- Final schedule and site handover dates to be coordinated with DESCO.
2. Sequence of major activities
- Mobilization & site survey — verify alignment, locate existing utilities, mark handhole and crossing locations.
- Traffic & safety setup — temporary traffic management, signage, and barricades for road crossings.
- Duct pipe laying — trenching, bedding, laying ducts, warning tape, backfill, compaction.
- Handhole construction — excavate, formwork, reinforcement, cast concrete chamber to specified dimensions, install cover and frame.
- 100 mm PVC road crossing — install sleeve/conduit with proper encasement and warning markers.
- Cable blowing — pre-clean and test ducts, blow optical fiber using a blowing machine, monitor tension and speed.
- Termination & testing — splice, test OTDR, and end-to-end loss, document results.
- As-built & handover — drawings, test reports, material certificates, completion certificate.
3. Method statements (short)
- Duct laying: Trench depth per local standard; sand bedding; ducts laid with minimum bending radius; joints sealed; warning tape 300 mm above ducts.
- Handholes: Concrete grade and reinforcement per structural requirement; internal benching and cable entry sleeves; corrosion protection for metallic parts.
- Cable blowing: Use a calibrated blowing machine; lubricants compatible with cable sheath; maintain blowing pressure logs; avoid pulling where possible.
- Road crossing: Use 100 mm PVC sleeve; concrete encasement where required; install end seals and marker posts.
4. Quality, testing, and acceptance
- Inspections: Pre-backfill inspection for ducts and handholes.
- Tests: Continuity and insulation checks for ducts (where applicable); OTDR traces and insertion loss for each fiber; power meter and light source verification.
- Acceptance: Tests must meet DESCO-specified thresholds; provide OTDR plots and splice logs.
5. Health, safety, and environment (HSE)
- Appoint an HSE officer on site.
- Provide PPE for all personnel; daily toolbox talks.
- Traffic marshals for road works; night works only with permits and lighting.
- Waste management plan for excavated material and concrete washout.
6. Mobilization checklist (minimum)
- Project team and contact list.
- Equipment: excavators, compaction tools, duct-laying rollers, cable blowing machine, OTDR, fusion splicer.
- Materials: ducts, 100 mm PVC pipes, handhole materials, warning tape, sand/gravel for bedding.
- Permits, traffic management plan, utility clearance.
- Transport vehicles for material movement from the DESCO store.
Preliminary timeline (example, adjustable)
- Week 0–1: Mobilization, survey, permits.
- Week 2–4: Duct laying and handhole construction (phased by section).
- Week 5: Road crossing installations and final civil works.
- Week 6: Cable blowing, splicing, testing.
- Week 7: Documentation, punch-list, handover.
Deliverables to DESCO
- As-built drawings and GIS coordinates.
- OTDR traces, insertion loss, and splice logs.
- Material certificates and inspection reports.
- Completion certificate and maintenance recommendations.
We are ready to shape your project. You may contact us for your requirements. Contact